Adding a switching sequence

Adding a switching sequence

This screen is used to create or edit switching sequences. Click on any of the orange call-outs to read more about a specific field or option.

1Channel selection

Channel selection
Select the channel to define a record for.

2Day selection

Day selection
Select the day of the week to define a record for.

3ON time

ON time
Select an ON time (when the channel will be activated or switched on)

4Duration

Duration
Enter a duration in hours, minutes and seconds. The system will calculate the correct OFF day and time from the duration, which may not exceed 23:59:59 - if you need a longer period than this, define a second period with start day and time EXACTLY the same as the end day and time of the previous period: The system will then IGNORE the OFF day and time event completely.

5OFF day/time

OFF day/time
The system will calculate these values from the start day/time and duration values.

6Quit button

Quit button
Click to close the screen without saving changes.

7OK button

OK button
Click to save the screen as shown.

8Help button

Help button
Click to access the online help (this document).